Use the Criteria page of the Reclass wizard to select the portion of the project that you want to reclass.
Contents
Field | Description |
Criteria
|
Click the drop-down menu and select one of the following options:
- Total Project
- Control Account
- Work Package
- WBS
- OBS
- WP
- Resource Assignment
- Resource
- Control Account.Location
- Work Package.Charge Number
- CAM
- Work Package Manager
|
Selection
|
Cobra enables this field if you selected a criterion other than
Total Project in the
Criteria field. Click
to display a dialog box that lists all valid options based on the selected criterion. For example, if you selected Control Account as the criteria, the Control Account Lookup dialog box displays, showing all control accounts used in the selected project.
|
Include all children
|
This check box is available if you selected a code validated with a code file in the
Selection field. Selecting this check box instructs Cobra to run the reclass process against any code assignments with the selected code and its children. For example, if you selected WBS code 1.1 in the
Selection field and selected the
Include all children option, control accounts and/or work packages with a code assignment of 1.1 or any child codes, such as 1.1.1 and 1.1.2, will be included in the reclass process.
|